SEVEN cases of landslides, six in Selangor and one in Negeri Sembilan, were reported by the Minerals and Geosciences Department (JMG) as at 10am on the first day of this year.
The National Disaster Management Agency (NADMA), in a statement yesterday, said that with the additional incidents, this brings to a total of 140 landslides occurring during the northeast monsoon (MTL).
“JMG has informed the occurrence of landslides in the affected areas to the respective local authorities to submit a report to the state JMG for landslide inventory during MTL 2021/2022,” it said.
According to the statement, the Public Works Department reported incidents of disaster, including floods, landslides, road collapse, damaged or collapsed bridge, at 53 locations as at 10am yesterday.
Meanwhile, the Malaysian Communications and Multimedia Commission said a total of 1,007 or 96% of the 1,039 communication infrastructures that were affected by the floods have been repaired.
It said, based on cumulative data starting Dec 19, the remaining 32 communication structures are still under repair, while those that have been fully repaired were in Kuala Lumpur, Putrajaya, Port Dickson, Rembau, Seremban, Pekan, Raub, Kuala Langat, Kuala Selangor and Gombak.
Apart from that, NADMA said that as of December 30, the Housing and Local Government Ministry reported that SWCorp Malaysia had completed cleaning works in 85% of the flood-affected areas in five states.
The states are Pahang, Melaka, Negri Sembilan, Kuala Lumpur and Selangor with an estimated total waste of 2,269 tonnes at the transit site and 4,142 tonnes at other landfills.
The cleaning work involved 2,286 workers and 908 machineries, it stated.
Meanwhile, following the update on the Continuous Bad Weather Warning by the Meteorological Department (MetMalaysia), an updated Disaster Operations Preparedness Notice has been issued by the National Disaster Control Centre.
“All disaster management committees at the state/district level must be activated and the level of preparedness enhanced to face impending disasters, especially in high-risk areas.
“The state/district disaster management committees are also requested to ensure that all relief centres are equipped with basic necessities, and that the control post on scene has all sufficient operational assets and is in good condition and ready for use,” NADMA noted.
It also informed that MetMalaysia and the Irrigation and Drainage Department will provide early notification that is updated from time to time, so that all Disaster Operations Control Centres can be prepared. – Jan 2, 2022.